|
If you are a contractor or geotechnical special inspector who
will be conducting grading activity in an Environmentally Critical
Area (ECA) during Seattle's wet season (October 31-April 1),
you need to start planning early to obtain a dry season extension
letter from DCLU and avoid a stop work order.
In consideration of slope stability and soil erosion, the
Seattle Municipal Code requires that all grading in ECAs must
be completed or stabilized by October 31 each year, unless it
can be proven to DCLU that no environmental harm or safety problems
will result (SMC
25.09.060 C9).
Overview of Dry Season Extension Requirements
For permits issued prior to October 1 in a given year:
- The geotechnical engineer must send a letter to DCLU by
October 7 providing the schedule for completing the grading
work.
- If the schedule shows that the grading and site stabilization
will continue past October 31, a Dry Season Extension Application
must be filed with DCLU no later than October 15. DCLU will
process these applications as soon as possible, but if the
extension is not approved by October 31, the contractor must
stop any grading and stabilize the site immediately.
- If the schedule shows that all grading will be completed
by October 31, then a letter from the geotechnical engineer,
stating that the grading was competed and site stabilized,
must be submitted to DCLU no later than October 31.
For permits issued between October 1-April 1 in a given year:
- No grading work can start after October 1 for projects subject
to dry season restriction unless the contractor submits, on
or before the date of permit issuance, a schedule approved
by the geotechnical engineer showing that grading will be
completed by October 31.
- No grading can occur without the dry season extension approval
for permits issued after October 31.
- DCLU's Site Development team will issue a stop work order
on November 1 on projects that are not in compliance with
Director's Rule 3-2002 (see box at top right).
|
|
|
|
| |
Extension
Requirements & Criteria |
|
The application requirements and criteria
for an extension are detailed in a new DCLU Director's
Rule (DR
3-2002) that became effective July 1, 2002. Be sure
to review your inventory of current projects located within
the City of Seattle and be prepared to comply with the
process and time frames outlined in this rule.
Paper copies of DR 3-2002 are
available from the Public
Resource Center, located on the 20th floor of Key
Tower at 700 Fifth Ave.
|
|
If, after reading DR 3-2002, you have questions regarding
its requirements, please contact:
Susan Chang
DPD Site Development Supervisor
susan.chang@seattle.gov
(206) 386-9785
|
|