John Street Enhancement
|
||||||||
| LOCATION |
Summit Ave E and E John St
|
| BUDGET |
The Opportunity Fund allocates $260,000 for this project.
|
| SCHEDULE |
Planning: January - March 2012
Design: April 2012 - April 2013
Construction: May - September 2013
Completion: Fall 2013
|
This proposal enhances the new park and P-patch by adding a bioswale, planting area and providing better pedestrian connections.
This project was selected for the first round of Parks and Green Spaces Levy Opportunity Funding. The application received
in this community-initiated process is a preliminary concept and the final design may be constrained by the project budget. All projects will go through Park’s public involvement procedure which includes public meetings and community input. They will also go through an internal Parks process to ensure the most effective implementation.
*Note: To view a PDF, you must have Adobe Acrobat Reader. Download it for free at www.adobe.com.
There are no events scheduled at this time.
Emily Lofstedt
800 Maynard Ave S
Suite 300
Seattle, WA 98134
206-684-7047
emily.lofstedt@seattle.gov
|
|
| Home | Partnerships | Park Board | Volunteer | FAQ | Parkways Blog |
|
|