Oxbow Park Pro Parks Project Information
A vacant lot 6400 block between Carleton Ave. S. and
Corson Ave. S.
Click to skip down to:
PROJECT STATUS
FOR MORE INFORMATION:
Kelly Davidson
800 Maynard Ave. S., 3rd Floor
Seattle, WA 98134-1336
206-684-0998
kelly.davidson@seattle.gov
EVENTS:
There are no events currently scheduled
|
Restoration of the hat is underway!
The Georgetown Community Council, in collaboration with Seattle
Parks and Recreation, restored the boots in 2005. Restoration on
the hat is currently in progress and expected to be completed in
the 4th quarter 2008.
Thank you, Seattle! This Pro Parks project is complete, and the
park is open to public. On Saturday, August 13, 2005, the community
gathered to dedicate the new park.
Park construction started in November 2003 but it took on real
meaning with the move of the Hat 'n Boot structures to the park
on December 13, 2003. The move was accomplished in two stages
starting on December 12. (See photos.)
| LOCATION |
A vacant lot 6400 block between Carleton Ave. S.
and Corson Ave. S.
|
| BUDGET |
The authorized Pro Parks budget for the project
is $335,075.
The Georgetown Community Council (GCC) has been awarded a Department
of Neighborhoods Matching Fund award of $122,454 and several other
grants to help fund park development.
|
| SCHEDULE |
Planning: 2001-2002
Design: 2002-2003
Construction: 2003-2004
Completion :2004
|
|