Thank you, Seattle. This Pro Parks Levy project is now complete!
Construction of Phase 2 has been completed, including shoreline improvements at the Magnuson Off-leash Area. Off-leash beach access is now open! Visit the Magnuson Park Off-Leash Area web page for additional project information.
LOCATION
BUDGET
The Pro Parks Levy provides $700,000 project costs of planning, design and construction.
SCHEDULE
Planning:Complete
Design:Complete
Construction:Complete
Completion:Completed in January 2005
PROJECT DESCRIPTION
Implement phase two of Pro Parks Levy funded off-leash area improvements:
shoreline restoration and mitigation planting.
Thanks to the Magnuson Off-Leash Group, Denny Middle School students and numerous volunteers for their support planting native plants in the off-leash area!