Montlake Community Center Pro Parks Project Information
1618 E Calhoun St
Click to skip down to:
PROJECT STATUS
EVENTS:
On Friday, Jan. 5, 2007 Mayor Greg Nickels joined Seattle Parks
and Recreation and the community for the grand opening celebration.
FOR MORE INFORMATION:
Dan Johnson
800 Maynard Ave S. 3rd Floor
Seattle, WA 98134
206-684-7149
|
Thank you, Seattle!
This project is complete.
In spite of material cost increases and delays for the concrete drivers
strike in the fall, this project remained on schedule and within budget.
During Construction, Parks staff met with the Montlake Advisory Council
to discuss the desired improvements to the Tudor building raised in the
Community Meetings. Due to the rapid escalation in construction materials
costs, the project budget could not accomplish all of the desired improvements
to this building.
Special thanks go to the Montlake Community Center Advisory Council for
donating $42,000 in additional funding specifically designated to improve
the Tudor building, preserving its exterior and upgrading the interior finishes.
For a full review of the public involvement process, please see Montlake
Community Center Public Involvement Summary . (PDF)
| LOCATION |
1618 E Calhoun St
|
| BUDGET |
The Pro Parks Levy provides $3,385,670 project
costs for planning, design and construction.
|
| SCHEDULE |
Planning:2004
Design:2004-2005
Construction:Spring - Winter, 2006
Completion:Winter, 2006
|
PROJECT DESCRIPTION
To improve Montlake Community Center by expanding activity areas, and create
a multipurpose room, showers, and office space.
COMMUNITY PARTICIPATION
Public Meeting #1 10/14/04
Meeting Notes PDF
Preliminary concepts
(PDF)
Carlson Architects worked with the PAT to further revise the concepts,
based on the PAT's and the community's preference to build an addition
to the gym rather than joining all buildings or adding to the "Tudor"
building.
> Refined concepts (PDF)
Project Advisory Team
Members are:
John Bakken
Robin Bentley
Ted Choi
Febe Cude
Shane Doran
Alfonso Marsh
Johanna Richey
Ken Schubert III
Meetings:
August 30, 2004 notes
(PDF)
October 25, 2004 notes
(PDF)
November 15, 2004 notes
(PDF)
March 23, 2005 notes
(PDF)
July 7, 2005 notes
(PDF)
IMPORTANT LINKS
|
< A-Z Projects List <
Acquisition < Development
< Project Map |
| |
| Updated 4/16/2007 16:46 |