Marion Street – Western Avenue to Sixth Avenue
|
|
|
September 18, 2009
Construction Restarting on Marion Street Mostly Night Work for Next Three Weeks
September 10-11:
- SDOT’s contractor will do daytime saw-cutting work in preparation for asphalt base repair next week. There will
be some periodic lane closures and parking restrictions on Marion Street between Western and Sixth avenues.
September 14-18:
- The contractor will restart major work on Marion Street repairing the roadway base to the asphalt section of the
street and adjusting utilities between Western Avenue and Sixth Avenue. The base repair will occur during the night shift, 6:00 PM to 6:00 AM, September 14-17.
- Traffic will be reduced to one lane 24/7 between Western and First avenues and one lane during non-peak hours between First and Fifth avenues. Marion will be periodically closed between Fifth and Sixth avenues
for base repairs.
September 18-19:
- Construction crews will grind and remove the old asphalt surface. The work will be done at night and on a weekend, 7:00 PM Friday evening to 6:00 AM Saturday morning.
- There will be parking restrictions, and traffic will be reduced to one lane on Marion Street. There will be
brief crossing restrictions at intersections.
September 21-23:
- Asphalt paving crews will pave Marion Street along the entire stretch of roadway between Western and Sixth avenues. The concrete section of roadway has already been paved. The work will be done at night, 6:00 PM to 6:00 AM each day.
- There will be parking restrictions, and traffic will be reduced to one lane on Marion Street. There will be temporary crossing and turning restrictions at intersections.
September 24-30:
- Construction crews will install temporary and permanent pavement markings, and substantially complete the project.
- There will be some periodic lane closures and parking restrictions
The above schedule depends on weather conditions.
September 15, 2009
There had been a two week shutdown of major work activity on Marion Street
from the end of August until late last week.
Over the next two to three weeks construction crews will work mostly night
shifts, but also day shifts, repairing the roadway base to the asphalt
section of the street, adjusting utilities, grinding and removing the old
asphalt surface, overlaying a new asphalt surface (nigh time work), and
installing temporary and permanent pavement markings. Expect traffic to be
reduced to one lane on Marion Street during non-peak day time hours and
during night time work.
|
The Seattle Department of Transportation (SDOT) is making improvements to several arterials in Downtown Seattle in 2009. The projects are funded by the “Bridging the Gap” transportation levy approved by Seattle voters in November 2006.
SDOT is planning to make improvements to Marion Street, between Western Avenue and Sixth Avenue, starting in late July or early August 2009. The project is expected to be completed by early October 2009.
Project Description
The project will include new concrete and asphalt pavement, upgraded curb ramps, and some areas of replaced sidewalk.
Originally scheduled for 2010 construction, this project was accelerated as part of the Mayor's economic stimulus package, called "Seattle Jobs Forward", to create jobs and revive the local economy. The "Seattle Jobs Forward" is a package of immediate local action to create direct jobs and boost Seattle’s economy over the next two years.
What to Expect During Work
- Lane closures
- Pedestrian and vehicle detours
- Parking and loading restrictions
- Moderate construction noise and dust
- Week day & weekend work activity
- Some night work
- Regular notices with additional information during construction
- Access maintained to all businesses and residences