Intermediate Capacity Transit Study
Stage 1
In Stage 1 of the Seattle Transit Study the Project Management Team considered more than 45 potential routings drawn from neighborhood plans, previous studies, public suggestions and professional judgement. Seven broad corridors were selected for further study. The corridors and potential technologies were presented to the public at two open houses in October 2000. The Team identified five of the seven corridors as potentially feasible:
- Aurora/Greenwood/Downtown
- Ballard/Fremont/U-District
- Downtown & environs
- Lake City/Northgate/Ballard/Downtown
- West Seattle/Downtown
Feasibility was determined by several key factors:
- Ability to carry existing and new transit riders
- Cost of implementing technology
- Potential impacts within the corridors
Stage 1 Recommendations
The Lake City/Northgate/Ballard/Downtown and West Seattle/Downtown corridors were chosen for further analysis.
Future studies will provide a similar level of analyses on the other potential corridors which may eventually make up an ICT system.
Stage 1 Supporting Documents
Review of Phase One Recommendations
Review of Previous Relevant Studies
Proposed Evaluation Process and Criteria
Finalization of corridors and selection of specific "sample routes within corridors
Compilation of preliminary transit travel demand forecasts and ridership projects for Study routes
Development of conceptual plans for ICT transit services along Study corridors and routes.
Preliminary identification of environmental impacts along Study route
Development of preliminary capitol and operating costs for sample routes
Summary of Findings
|