Status Update: Final Report for 1999

December 30, 1999

Prepared by
City of Seattle Y2K Project Office
Marty Chakoian
Y2K Project Manager

The information provided in this report is produced for the sole purpose of assisting the planning for the transition to the Year 2000. All information provided is hereby designated a Year 2000 readiness Disclosure Statement as defined in section 3 (11) of the Year 2000 Information and Readiness Disclosure Act, (Public Law 105-271, 112 Stat. 2386).

Introduction

The City of Seattle, like most state and local governments and large businesses, has very nearly completed the work of updating or replacing its major computer systems in preparation for the Year 2000. In the last days of 1999, the City is concentrating on carrying out its plan for staffing, monitoring, and reporting on its most vital systems and operations over the New Years Weekend.

This report is a snapshot of the City’s situation on December 30, 1999. Current information is also available on the City’s Y2K web site at http://www.ci.seattle.wa.us/y2k/

  1. Background
  2. Last fall, the City contracted with Data Dimensions, Inc., to review its Y2K readiness program. Their assessment was released in February of this year. Although they did not identify any critical systems that were likely to fail, the review pointed out weaknesses in the City’s processes which could put it at high risk when computer systems roll forward into the Year 2000.

    At the time of the review in the fall of 1998, the City’s departmental approach lacked efficiency, coordination and consistency. Individual departments varied widely in their ability to manage, staff, and fund a comprehensive Year 2000 effort. There was no central supervision or control and consequently, clearly defined plans and consistent methodologies were not being used across City departments.

    Since the distribution of the Data Dimensions report in February, the City has established a Y2K Project Office and adopted a date standard and methodology. The Y2K Project Office has promulgated that methodology and attendant forms and procedures, developed an overall project plan with milestones and dates, and established facilities to assist with testing. Departments -- working with the staff of the Project Office -- have prioritized, scheduled, and mostly completed accomplishing their work.

  3. Computing and Communications Infrastructure
  4. One important aspect of the Y2K project has been to ensure that the City's desktop computers and local area networks are at the level of Y2K compliance. The Citywide Desktop Standardization Project has worked with departments to inventory the City’s PCs and to replace those with Y2K related problems. We inventoried 7965 PCs used by City departments; many of these PCs have been upgraded or replaced. As a result, 100% of the City’s PCs are now Y2K-compliant. Software patches for Windows, NetWare, and GroupWise have been installed. The City’s fiber backbone data network has been upgraded and a new Police 911 Center installed at the new West Precinct has been certified by the vendor as Y2K-compliant and has been successfully tested end-to-end with U.S. West. Likewise, other key elements of our computing and communications infrastructure, including emergency radios and mobile data terminals, have been determined to be Y2K-compliant.

  5. Computer Systems and Applications
  6. Most department efforts have been focused on fixing applications that support the City's primary business functions. Departments have identified 89 mission-critical applications. As of this report, all 89 of the systems have been fixed or replaced.

    Date Activity Status
    December 20 Fix or replace computer systems 89 of 89 complete
  7. Testing and Certification
  8. Once departments have finished fixing their applications, our approach is to certify each system as compliant through rigorous, formal testing under the review of the Y2K Project Test Team. To date, 88 systems have been tested and certified. One, the Municipal Court Information System, has been fixed and tested by its owning department. Its late date of completion precluded formal review and certification of the test results by the Y2K Project Test Team.

    Date Activity Status
    December 20 Certify systems through formal testing 88 of 89 complete
  9. Embedded Systems
  10. The term embedded systems is used to refer to computer chips and software embedded in equipment that is used in day to day business operations. Examples include HVAC systems, fuel pumps, alarms, and process controllers.

    The City has now completed an aggressive examination of its embedded systems, using both expert City staff and consultants. (The Y2K Project Office especially recognizes the fine work of staff from DCLU, Seattle Center, and ESD who have assisted in this area.) The utilities have reviewed controllers used in the distribution of water and electricity and in the removal of wastewater and operation of the solid waste transfer stations. The Police communication equipment and Fire stations, fire boats, and emergency medical equipment have been carefully inventoried and assessed. Even the systems which help to operate the Zoo and the Aquarium have been surveyed to ensure that animal life will not be jeopardized by Y2K related errors.

    Date Activity Status
    December 20 Assess and fix or replace embedded systems 100% complete. No significant problems identified.
  11. Vendors and Suppliers
  12. Like most public or private organizations, the City of Seattle cannot function without the products and services it receives from its business partners. We depend not only on cooperation and support from other government agencies—the federal government, the State of Washington, King County—but also from the private sector. We have therefore identified and surveyed our most critical suppliers: large firms such as US West, Seafirst Bank, and others, along with smaller companies on whom we depend for supplies and equipment. Thus far we are reassured by the serious approach which these companies are taking to address their own Y2K issues; any lapses in their ability to serve us have been addressed in our contingency plans.

    Responsible Party Activity Status
    Departments Identify key vendors and suppliers 100% complete: 346 identified
    Departments Evaluate key vendors and suppliers 100% complete through readiness assessment and/or contingency planning
    Y2K Project Staff Evaluate vendors and suppliers common to more than one Department
    • 62 common vendors/suppliers identified (in addition to the 346 Department-specific vendors and suppliers).
    • 62 evaluated.
    • 61 found to be low-risk, with no issues.
    • 1 found to be at some risk; contingency plan developed.
    • All rechecks completed.
  13. Contingency Planning
  14. The one certainty about Y2K is that something somewhere will go wrong. Therefore, departments developed contingency plans to help ensure that the public will continue to receive basic services without interruption. A workshop was held this spring in conjunction with the State of Washington. A web page, http://inweb/Citytech/y2k/cp/default.htm, was established on the City’s Y2K project site, and briefings were held with each department to provide guidance.

    Department staff worked hard to develop realistic short term workarounds for areas of potential vulnerability, should any of our own systems fail or our vendors or suppliers be unable to meet their obligations to us. To assist this effort, a matrix was created to identify interdepartmental dependencies on items managed by another department. While departments were responsible for individual exercises to test and validate their plans, two City-wide exercises have been conducted to ensure that those plans are realistic and coordinated.

    Date Activity Status
    October 19 Citywide Contingency plan exercise focusing on vital operations and services Exercise held; results documented and distributed
    December 8 Citywide Contingency plan exercise focusing on financial business processes and computer applications Exercise held; results documented and distributed
    December 30 Complete contingency plans All 15 departments submitted initial plans to the Y2K Project Office for review. Subsequently, all 15 departments submitted revisions in accordance with our evaluation recommendations and are now "completed and confirmed".

     

  15. Rollover Period Preparation
  16. The "Rollover Period" is officially defined as the period between December 28, 1999, and January 4, 2000. During this time, departments are assigning extra staff to monitor and report on mission-critical computer systems. In addition, the Y2K Project office, in coordination with the City’s Emergency Operations Center, is bringing together public safety agencies, utilities, the Executive Services Department, and others to ensure uninterrupted delivery of essential City services, and to report on the status of such services and key systems to the State, to the Federal government, and to the public.

  17. Public Involvement
  18. Seattle City government’s focus during the first half of 1999 has been to inventory, assess, and fix its own Y2K problems. However, Seattle’s success in moving smoothly into the new year will be measured not just in how government services perform, but in how our whole community transitions. Individual and neighborhood preparations are as important as the preparations of City departments. In addition to some excellent work by the City’s Emergency Operations Center in promoting general preparedness through activities such as Disaster Saturday, a more comprehensive, Y2K-specific preparedness program was developed. It includes a comprehensive set of brochures, a video, press events, and direct participation in community forums.

    Recently, the Y2K Project Office produced and aired four cable access programs on Y2K. Copies of these programs are available through the public libraries.

    The final phase of the public information program is to prepare the public for the New Year’s weekend (December 31— January 2). A flyer is being mailed to all households in the City and a 30-second public service announcement is being distributed to local television stations. During the New Year’s weekend, public information staff will provide the public with regular updates through the media on the status of our City’s mission-critical systems and services.

  19. First Quarter 2000 Assessment
  20. While much attention is focused on events occurring on December 31 through January 2, many believe that the real impact of Y2K will occur as problems emerge and compound throughout the coming year. The Y2K Project Office is creating and implementing a mechanism for identifying those problems and their impacts, developing remediation strategies, and prioritizing and tracking the work to completion.

  21. Collateral Benefits

Y2K efforts in the City and elsewhere are generally focused on assessing risk and fixing problems; our explicit goal is that the City will be able to operate next year just as it does today. Thus, a significant investment of effort is being made merely to maintain the status quo.

Nonetheless, many aspects of the City’s Y2K program will have a lasting, positive impact and are therefore worth noting. These include

If continued and built upon, these advances can create the foundation for a significantly higher level of professionalism and performance across the City’s computing environment for years to come.

Status by Department

The following is a report on the Y2K effort by each of thirteen City departments and a single grouping combining information for smaller departments. The purpose of this information is to provide a complete picture of each department’s ability to ensure continued service to the public.

For each department, we have identified:

The number of PC’s and the percent that are now Y2K-compliant. This project will not only ensure that desktops are ready, but it will also culminate in standardization that will enable the City to be more efficient and cost effective.

The number of mission critical applications (those that a department has identified as essential to the continued performance of their business functions); the number of these for which Y2K work has been completed; and the number which have been certified through additional testing under the review of the Year 2000 Project.

The name and status of each mission critical application supporting the department, including remediation status ("complete" or the date by which remediation is to be complete), and certification status ("certified", or the date by which certification is expected).

The number of minor applications (those that a department has identified as having little impact or easy work-arounds) and the number of these for which Y2K work has been completed.

The number of vendors or suppliers of goods and services important to the department, and the number of these which have been contacted to assess Y2K readiness.

The strengths and weaknesses of each department’s Y2K program as noted by an independent quality assurance assessment. This quality assurance review evaluates methods used and the processes employed as a department works toward compliance.

The status of the department’s contingency planning efforts. For instance, how they’ve determined to use additional staffing, manual operations, or lower technology equipment in case there is an unforeseen problem.

Any issues that highlight efforts under way or illustrate key challenges faced by the department.

City Light

Department Overview

Desktops

# of PCs 1450 % Y2K compliant 100%

Mission Critical Applications

# of Applications 15

# Y2K Work Completed 15

# Certified Compliant /Ready 15 (14 certified compliant; 1 ready with workaround)

Name Description Remediated Certified
AMPS (includes timesheet) AMPS is an operations-oriented program whose purpose is to help City Light manage its tracking of field work and labor hours. Complete Certified
CIS/CMS (Cust Info Sys/Credit Mgt Sys) CIS is the repository for Seattle City Light residential and commercial customer information. It contains address, premise, and payment information. CMS is designed to improve collector productivity, collection effectiveness and management control. Complete Certified
Daily Rate Special rating system for very large customers, rates are calculated thru this app for manual billing. Complete Certified
DAMS GIS (Dist Automated Mapping Sys) An Arc/Info based model of SCL's electrical distribution system. SCL's quarter section and feeder maps are generated from this system. Complete Certified
ESS (Electrical Systems Status ) Web page summary of electrical distribution status. Complete Certified
EMS (Energy Mgt System) SCL Integrated Control system for electrical power transmission & distribution Complete Certified
Flat Rate Excel Spreadsheet based rating system. Bills low-use rates for customers with multiple locations. (manual billing) Complete Certified
ICSB (Industrial & Commercial Subsidiary Billing) ICSB is a billing system for SCL large commercial and industrial customers. (ie Boeing) These are not able to be billed appropriately thru the other billing systems. Complete Certified
LPS (Logility Planning Systems) MMS and LPS together make up City Light's primary inventory system, responsible for nearly 17 million dollars of material used by the crews of City Light in their daily work. These two systems track, issue, plan, report, and help manage this inventory asset. Complete Ready with workaround
MMS (Materials Mgt System) MMS and LPS together make up City Light's primary inventory system, responsible for nearly 17 million dollars of material used by the crews of City Light in their daily work. These two systems track, issue, plan, report, and help manage this inventory asset. Complete Certified
NETGIS Netgis application is an Oracle-based geographic information system with a highly customized AutoLisp-driven AutoCAD user interface, used primarily by the Network Distribution System. Complete Certified
PDMS Workflow Used to manage and track AutoCAD drawings and revisions. Complete Certified
Sundry Sales Sundry sales is used to bill customers for services that CIS and ICSB cannot handle. Most bills are one-time bills, long-term accounts are handled manually. Complete Certified
Transformer This system is used to inventory and track all transformers, and maintain transformer events history, including installation, upgrades, removals, etc. Complete Certified
Wintercress (includes timesheet) Automated maintenance management system that schedules and tracks corrective repairs (Trouble Calls) and preventive maintenance (PM's). It is used to track daily costs, project PM's, maintenance on equipment and perform reporting and operations of any maintenance activities in the Power Stations & Power Generation divisions. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
21 21

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
84 84

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resource, direction, coordination, communication, staffing, controlling, seeking remedies, and contingency planning.

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Design, Construction and Land Use

Department Overview

Desktops

# of PCs 350 % Y2K compliant 100%

Mission Critical Applications

# of Applications 4

# Y2K Work Completed 4

# Certified Compliant 4

Name Description Remediated Certified
Access Apps for Annual Maintenance Inspection Three different Access databases that track boiler, elevator, and refrigerator inspections and permits. These applications interface to the Platinum Accounts Receivable System. Complete Certified
Accounts Receivable System (Platinum) Manages permit payments. New System in production December, 1999 Certified
OTC (Over the Counter Permitting Sys) Issuance of small, residential permits at the Walk-In Center; handles inspection scheduling and maintains inspection results. Complete Certified
PTS (Permit Tracking System) Manages and tracks the issuance of permits. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
2 2

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
1 1

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resource, direction, coordination, communication, staffing, controlling, seeking remedies, and contingency planning.

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Executive Services Department [ESD]

Department Overview

Desktop

# of PCs 900 % Y2K compliant 100%

Mission Critical Applications

# of Applications 8

# Y2K Work Completed 8

# Certified Compliant 8

Name Description Remediated Certified
ACH (Automated Clearing House) Enables wire funds transfer. Complete Certified
Banctec/RPS Captures payment information from City’s major billing systems. New software into production: 9/30/1999 Certified
B&O Tax System Accepts and posts B & O tax payments. Complete Certified
CRS (Cash Receiving System) Processes payment information for input to Summit. Complete Certified
CSS HRizon (HRIS) City’s employee pay and benefits system Complete Certified
Muni Court Payments Processes payments received from Muni Court. Complete Certified
RAPS Accepts payments from remote locations. Complete Certified
Summit City’s financial system. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
97 68

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
22 22

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resource, direction, coordination, communication, staffing, controlling, seeking remedies, and contingency planning.

Weaknesses: None noted.

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Fire

Department Overview

Desktops

# of PCs 200 % Y2K compliant 100%

Mission Critical Applications

# of Applications 10

# Y2K Work Completed 10

# Certified Compliant 10

Name Description Remediated Certified
911 Call Recorder ANI/ALI and call data Complete Certified.
Arson Case Management Tracks and manages arson investigations. Complete Certified.
CAD (Computer-Aided Dispatch) Fire/EMS personnel, radio, apparatus, address, GIS and other data used for dispatching. Complete Certified.
Certification Test Tracks companies and individuals certified to test safety systems, and generates tests. Complete Certified.
FMO -- Plan Review Database Tracks information on New Plans that are submitted to FMO Fire and Life Safety Mgmt. Complete Certified.
Payroll -- FLSA Monitoring Tracks time off/on duty by FLSA category for monitoring purposes. Complete Certified.
Payroll Worksheets Generates payroll time worksheets Complete Certified.
Permit Tracking System Fire Code permit and billing/receipt information management Complete Certified.
Purchase Order Log Purchase request data Complete Certified.
RMS (Records Mgt System) Fire/EMS incident history and a fire/haz-mat/rescue incident reporting program (called WAFIRS). Complete Certified.

Minor Applications

Number of small, non-critical applications Number fixed or replaced
23 Manageable 15

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
6 6

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resources, direction, coordination, communication, staffing, seeking remedies

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Human Services

Department Overview

Desktops

# of PCs 400 % Y2K compliant 100%

Mission Critical Applications

# of Applications 0

# Y2K Work Completed NA

# Certified Compliant NA

Minor Applications

Number of small, non-critical applications Number fixed or replaced
28 28

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
NA NA

Quality Assurance Assessment

Formal assessment not done due to small size of department.

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Law

Department Overview

Desktops

# of PCs 192 % Y2K compliant 100%

Mission Critical Applications

# of Applications 1

# Y2K Work Completed 1

# Certified Compliant 0

Name Description Remediated Certified
DAMION Tracks the management of misdemeanor cases and generates case documents. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
1 1

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
1 1

Quality Assurance Assessment

Formal assessment not done due to small size of department.

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Library

Department Overview

Desktops

# of PCs 482 % Y2K compliant 100%

Mission Critical Applications

# of Applications 1

# Y2K Work Completed 1

# Certified Compliant 1

Name Description Remediated Certified
Dynix Manages library inventories and controls circulation process. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
11 11

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
6 6

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, organization, financial resources, coordination, communication, staffing, seeking remedies, contingency planning

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Seattle Municipal Court

Department Overview

Desktops

# of PCs 281 % Y2K compliant 100%

Mission Critical Applications

# of Applications 1

# Y2K Work Completed 1

# Certified Compliant 0

Name Description Remediated Certified
MCIS (Municipal Court Information System) Supports Muni Court operations: scheduling, case tracking, recording payments, etc. Complete  

Minor Applications

Number of small, non-critical applications Number fixed, replaced or work-arounds in place
8 8

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
16 16

Quality Assurance Assessment

Department’s Y2K program is substantially acceptable and appropriately documented.

Strengths: Awareness, planning, organization, financial resources, coordination, seeking remedies

Weaknesses: None noted

Contingency Planning

Completed and Confirmed.

Issues

Municipal Court Information System (MCIS): Because Y2K testing revealed a number of problems, the Court decided to reverse its earlier strategy and has completed remediation of the system. Departmental testing to confirm that all fixes are working correctly for the rollover to January 1, 2000 is complete; a Leap Year (2/29/2000) problem that was previously identified has also been corrected. All changes have been implemented in the production system. The late date of MCIS remediation precluded formal review and certification of the test results by the Y2K Project Test Team.

Parks

Department Overview

Desktops/LANs

# of PCs 580 % Y2K compliant 100%

Mission Critical Applications

# of Applications 9; Recreation Business System will replace 4 systems.

# Y2K Work Completed 9

# Certified Compliant/Ready 9 (7 certified compliant, 2 ready with workaround. The workaround processes have all been tested. )

Name Description Remediated Certified
ARKS (Animal Record Keeping Sys) Animal inventory management that feeds data to ISIS for global animal tracking. Captures: identifiers, transaction data, enclosure data, weight, comments. Various internal reports: Supports multiple permit processes (USDA, US Wildlife, Export & Import). Vendor Compliant Certified
BBS (Blue Book System) Revenue tracking, generates journal entries into City’s SFMS/SUMMIT (incoming). Complete Certified
GRB (Group Reservation & Billing Sys) Track school/group visits, reporting. Complete Certified
Pool Admissions

Micros 2700 Hospitality Management System

For the Aquatics Divisions: Point of sale software that tracks monies and attendance, provides basis for departmental revenue collection and reporting. Will be replaced by Recreation Business System in February, 2000. Ready with workaround.
Zoo Admissions

Micros 3700 Hospitality Management System

For the Zoo: Point of sale software that tracks monies and attendance, provides basis for departmental revenue collection and reporting. Replaced: 9/27/1999 with Vendor Compliant system. Certified. Accepted vendor statement of compliance.
Med ARKS Animal medical records, pulls general inventory data from ARKS. Vendor Compliant Certified.
Recreation Business System (not counted in any totals) Will replace the Group Reservation & Billing System, the Hospitality Management Systems, and Recware. Vendor Compliant Certified for Y2K. In use at Aquarium & Zoo. Will be installed at rest of sites in Feb-Mar, 2000
Recware (DOS Version 7.2) Manage class registrations, prints out confirmation letter (with invoice amount, date, etc.). Reporting: End of Season financial reports, can do demographics. Will be used with a work–around. Ready with workaround.
RMS (Revenue Monitoring System) Reporting system: attendance count and revenue numbers. Complete Certified
SPARKS Single population animal records maintained by designated individuals (‘stud bookkeepers’) for each species. Data is sent to ISIS for global species planning (breeding, etc). Vendor will fix:

Fall, 1999

Certified.

Notes;

Recreation Business Systems (RBS): This will replace 4 systems: Group Reservation & Billing (GRB), Micros 2700 and 3700 Hospitality Management Systems, and RecWare for DOS. The Group Reservation and Billing System (GRB) has been Certified. The Micros 3700 system replaced the 4700 point of sale system at the Zoo and Aquarium on 9/27/99 and 10/11/99, respectively, and has been in full production since those dates. The Parks department has stated as part of the RBS Compliance Test that they consider this low risk and will accept the vendor’s statement of compliance. The RecWare Safari product is operating at two pilot sites for program registration. The Parks and Recreation Department is not satisfied with system stability and identified problems with some Safari functions such as point of sale (POS). Use of POS for pool admissions and deployment beyond the pilot sites will be delayed until February 2000. The admissions systems at pools will be handled using the work-around identified in their contingency plan – to set the date of each back to 1995 (which will roll over to 1996). This technique has been tested and is currently in use at the Green Lake Pool. The contingency plan for program registration is a manual system, although Parks has completed testing an alternative using the existing RecWare DOS program that can be used by community centers that wish to continue the existing processes. The tests indicate the system will operate acceptably in 2000 by scheduling programs and activities for 1972. The Department is currently scheduling activities for year 2000 dates by using 1972 as the program date.

ISIS software: The SPARKS application has a known Y2K problem in the data in a sub-application called GENES. Queries into an animal's genealogical data may produce inaccurate results after 1999. Parks has completed testing of the ISIS applications, and can perform their critical business functions without the use of the GENES component of the SPARKS Application.

Minor Applications

Number of small, non-critical applications Number fixed or replaced
138 70

Vendors/Suppliers

Number of critical vendors/suppliers Number at risk Number contacted to confirm readiness
70 31 31

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, direction, coordination, communication, staffing, seeking remedies

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Police

Department Overview

Desktops

# of PCs 850 % Y2K compliant 100%

Mission Critical Applications

# of Applications 3

# Y2K Work Completed 3

# Certified Compliant 3

Name Description Remediated Certified
911/Communications Center Processes incoming 911 calls and dispatches response; includes Call Center equipment and CAD application. Complete Certified
Pawnshop Automated Reporting System Reports pawnshop activity in accordance with State legal requirements. Complete Certified
RMS (Records Management System) Database of case & criminal histories, incident records, etc. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
70 69

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
23 23 contacted

Quality Assurance Assessment

Department’s Y2K program is substantially acceptable and appropriately documented, but needs moderate improvement to increase risk mitigation.

Strengths: Awareness, organization, financial resources, coordination, communication, seeking remedies

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

SEATRAN

Department Overview

Desktops

# of PCs 350 % Y2K compliant 100%

Mission Critical Applications

# of Applications 6

# Y2K Work Completed 6

# Certified Compliant 6

Name Description Remediated Certified
Accounts Receivable Generates customer invoices, tracks payments and balances, reports and posting to SUMMIT. Complete Certified
Annual Permits Bills annual permits for rental of ground or air space over City properties. Complete Certified
Equipment Cards Tracks time billed to equipment usage and loads the data to SUMMIT. Complete Certified
TimeCards Tracks time worked by regular FTEs and loads the data to SUMMIT. Complete Certified
Street Use Permits Processes permits allowing work in City streets. Complete Certified
UCIS Maintains an inventory of City Utility Cuts, schedules jobs, and tracks them to completion; feeds SUMMIT bills for reimbursement. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
41 41

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
15 15

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resources, direction, coordination, communication, staffing, controlling, seeking remedies

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Seattle Center

Department Overview

Desktops

# of PCs 187 % Y2K compliant 100%

Mission Critical Applications

# of Applications 4

# Y2K Work Completed 4

# Certified Compliant 4

Name Description Remediated Certified
Accounts Receivable Manages payment receipts for events. Complete Certified
Admission Dispatch Assigns event staff to specific Center events. Complete Certified
Payroll Entry Collects time information from regular and event staff, buffering to the HRIS payroll system. Complete Certified
SC EMS (Event Management Sys) Manages the scheduling of events and issuance of work orders. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
10 4

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
29 29

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resource, direction, coordination, communication, staffing, controlling, seeking remedies, and contingency planning

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Seattle Public Utilities

Department Overview

Desktops

# of PCs 1250 % Y2K compliant 100%

 

Mission Critical Applications

# of Applications 19

# Y2K Work Completed 19

# Certified Compliant 19

Name Description Remediated Certified
Combined Sewer Overflow Monitor and quantify instances of combined sewer overflows for regulatory requirements and emergency response. Complete Certified
Contact Time Analysis Supports operations and reporting of disinfection in water transmission system meeting state DOH regulations. Complete Certified
CUBS (Combined Utility Billing System) Bill residential and commercial customers for water, wastewater, and solid waste. Complete Certified
Emergency Resource Center Supports public information on status of emergency work in progress. Complete Certified
Flare Facility Control System (Kent Landfill) PLC Controlled burn-off of land fill gas emissions at Kent Highlands landfill. Complete Certified
Infrastructure Management System V7 (Drainage) Supports preventative maintenance, workload planning, inventory management, etc. for drainage and wastewater. Complete Certified
Interactive Voice Response -CS Provides automated access to selected SPU services information and customer account information. Complete Certified
ITRON Meter Reading Supports collection and transmission of residential and commercial water meter readings to and from the Combined Utilities Billing System. Complete Certified
IWRMS Data Entry Centralizes information on water sources, weather, flows, etc. supporting daily operations and planning. Complete Certified
IWRMS Reporter Centralizes information on water sources, weather, flows, etc. supporting daily operations and planning. Complete Certified
Laboratory Information Management System Supports water sample data management and prepares water quality regulatory reports. Complete Certified
One Call Utility Locator OCC Supports rapid response to requests utility line locations to ensure they are undisturbed by construction or digging. Complete Certified
One Call Utility Locator Sheds Supports rapid response to requests utility line locations to ensure they are undisturbed by construction or digging. Complete Certified
TimeCard Supports collection, validation, and payroll processing for employee hours. Complete Certified
Tolt Dam Monitoring System Regulatory requirement for Tolt earthen dam. Monitors sensors in an around the dam. Connects to alarm system for early warning in the event of dam failure. Complete Certified
Transfer Station Billing System Supports customer billing for transfer station services. Complete Certified
Wastewater Pump Station Network Monitors status of levels, pump run times, and power at 72+ wastewater pumpstations. Complete Certified
Work Management System (Water system) Supports preventative maintenance, workload planning, inventory management, etc. for water quality and supply. Complete Certified
Water Supply SCADA Supervisory Control and Data Acquisition System: controls the water network Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
124 124

Vendors/Suppliers

Number of critical vendors/suppliers Number contacted to confirm readiness
40 40

Quality Assurance Assessment

The department’s Y2K program is complete, thorough, and appropriately documented.

Strengths: Awareness, planning, organization, financial resource, direction, coordination, communication, staffing, controlling, seeking remedies, and contingency planning

Weaknesses: None noted

Contingency Planning

Complete and Confirmed.

Issues

None noted.

Small Departments

(Includes Department of Neighborhoods, Executive Department offices, Legislative Department, Hearing Examiner, Civil Service Commission, Arts Commission, Retirement Office, Police Pension, etc.)

Desktops

# of PCs 493 % Y2K compliant 100%

Mission Critical Applications

# of Applications 1

# Y2K Work Completed 1

# Certified Compliant 1

Name Description Remediated Certified
Retirement Contributions Tracking System Tracks employee retirement contributions. Complete Certified

Minor Applications

Number of small, non-critical applications Number fixed or replaced
5 - DON 4 - DON

Quality Assurance Assessment

Formal assessment not done due to small size of departments.

Contingency Planning

Department of Neighborhoods: Complete and Confirmed

Retirement Office: Complete and Confirmed.

All other Small Departments: Contingency plan review by Y2K Project Office determined to be optional.

Issues

None noted.

City Computing Infrastructure

Supported by the Department of Information Technology (DoIT)

The following systems support the City’s overall computing and communications infrastructure:

Mission Critical Applications

# of Applications 4

# Y2K Work Completed 4

# Certified Compliant 4

Name Description Remediated Certified
Network Backbone The City’s data communications network consisting of switches, routers and hubs which interconnect over 7000 computers in City government, ranging from mainframe computers to the desktop computers in most City offices. Complete Certified
Groupwise Messaging The City's e-mail/messaging system. Complete Certified
Novell Netware/NDS The underlying platform (both server hardware and software) for the City's messaging system. Complete Certified
City Phone System The City's private telephone network consisting of 25 major switches, over 130 minor ones, and over 10,500 individual telephone lines in about 300 City business locations. Complete Certified

 

Top of PageHomeSearchNewHotVisitorCitizenBusinessTipsFeedback